CAVE CREEK – Cave Creek will be seeing some construction this month.

The Town of Cave Creek has contracted roadwork for the mill and paving on Cave Creek Road south of Carefree Highway. This construction will run July 15-24. Drivers should expect delays during the roadwork.

From July 15-18, roadwork will focus on roadway patching and utility boxes and manholes. Starting July 19, workers will mill the roadway surfaces. From July 21-23, paving on the milled roadways is planned. On July 24, roadways that have been under construction will be restriped.

For more information, contact the Town of Cave Creek at (480) 488-1400.