ANTHEM – The Anthem Community Council Board of Directors voted in a special meeting on Dec. 5 to approve an amended bid to remodel the Anthem Community Center. The project is scheduled to be completed by late spring 2018.

The project includes a major overhaul for the community center and will cost over $800,000. The project has been discussed at several Board meetings in the past few months, and ACC staff has worked to reduce the costs and cut line items from the project where possible. The cost of the project will be covered from the Enhancement and Reserve Funds, according to ACC plans.

According to documents from ACC staff, the project includes:

Enlarging the reception desk to allow for more efficient customer services
Enclosing the unused balcony to create an expanded free weight/training area on the second floor
Painting refresh of some common areas
Re-carpeting throughout the second floor
Upgrading the free weight area flooring with new carpet and rubber padding
Adding storage for spin bikes, opening up space in the fitness room
Refinishing the wood floor in the fitness room
Modifying the first-floor office area to maximize limited administrative space and create a room for membership services
Incorporating added storage for program supplies 


No renderings of the planned remodel are available yet. Work is slated to begin on the project next week.